Most Salesforce projects that slip don’t slip in the build. They slip in week 2, when the scope never got signed off, or in week 10, when the data isn’t ready for the trial migration.
This page is the working checklist we use on projects, phase by phase, with an exit gate for each phase and a 12-week plan you can copy. For the bigger-picture guide, start with our how to implement Salesforce CRM post. This one is the template.
How to use this checklist
Each phase has tasks and a gate. Don’t start the next phase until the gate is met, or you’ll pay for it later.
The plan assumes a mid-sized Sales Cloud or Service Cloud rollout: 50 to 200 users, 1 or 2 integrations, and a data migration from a legacy CRM or spreadsheets.
Smaller projects compress it. Larger ones stretch it. Our post on how long a Salesforce implementation takes covers the variables.
Phase 1: discovery (weeks 1 to 2)
- [ ] Executive sponsor named and available weekly
- [ ] Project owner and Salesforce admin named on the client side
- [ ] Success measures agreed in numbers (for example, forecast accuracy, case response time, hours saved)
- [ ] Current processes mapped for each team in scope
- [ ] Requirements written as user stories and ranked must, should, could
- [ ] Out-of-scope list written and signed
- [ ] Integrations listed, with an owner on each other system
- [ ] Data sources listed, with record counts and a data owner per source
- [ ] Licenses and edition confirmed against requirements
Gate: scope, success measures and out-of-scope list signed by the sponsor.
Phase 2: design (weeks 2 to 4)
- [ ] Data model designed: standard objects first, custom objects only where needed
- [ ] Record types and page layouts designed per team
- [ ] Security model designed: roles, sharing rules, permission sets
- [ ] Automation designed per object, not per story
- [ ] Integration design: direction, pattern, frequency and error handling for each
- [ ] Reporting needs listed: the 10 reports and 3 dashboards leaders need on day 1
- [ ] Sandbox plan agreed (build, QA and UAT environments)
- [ ] Design reviewed against Salesforce’s Well-Architected framework principles
Gate: design walkthrough with the project owner, signed off. Changes after this go through change control.
Phase 3: build (weeks 4 to 8)
- [ ] Work planned in 2-week sprints with a demo at the end of each
- [ ] Building happens in sandboxes, never production
- [ ] Changes tracked in source control
- [ ] Each flow, object and integration has a description and owner
- [ ] No hardcoded IDs in flows, formulas or code
- [ ] Apex tests with real assertions, above the 75% deployment minimum
- [ ] Integration error handling and alerts built and tested
- [ ] Sprint demos attended by the people who’ll use the system
Gate: all must-have stories demoed and accepted by the project owner.
Phase 4: data (runs alongside build, weeks 3 to 9)
- [ ] Source data profiled: duplicates, missing values, invalid formats
- [ ] Cleansing rules agreed with data owners
- [ ] Field mapping signed off, object by object
- [ ] External IDs planned for every migrated object
- [ ] First trial migration into a sandbox by week 6
- [ ] Record counts and spot checks reconciled after each trial
- [ ] Final migration rehearsed end to end with timings
Gate: a full trial migration reconciles to the agreed record counts with no blocking errors.
Phase 5: testing (weeks 8 to 10)
- [ ] System test of every story in the QA sandbox
- [ ] Integration test with the other systems’ test environments
- [ ] User acceptance testing in a partial or full copy sandbox with migrated data
- [ ] Test scripts written as real tasks (“convert this lead and create a quote”)
- [ ] Defects logged, prioritized and fixed or deferred with sign-off
- [ ] Permission testing for every persona
Salesforce’s sandbox pricing page shows that a Partial Copy sandbox refreshes every 5 days and a Full sandbox every 29, so plan your UAT refresh before testing starts.
Gate: UAT sign-off from each business team, with no open critical defects.
Phase 6: training and change management (weeks 7 to 11)
- [ ] Training planned by role, not by feature
- [ ] Super users named in each team and trained first
- [ ] Short how-to guides and videos for the top 10 tasks
- [ ] Communication plan: what’s changing, when, and why, sent at least 3 times before go-live
- [ ] Old system access plan agreed (read-only date, switch-off date)
This phase gets cut first when budgets tighten, and it’s the one that decides adoption. Prosci’s Best Practices in Change Management research found that initiatives with excellent change management are 7 times more likely to meet objectives than those with poor change management.
Gate: every user has attended training or completed the self-paced course.
Phase 7: go-live (week 12)
- [ ] Go/no-go meeting held with the sponsor, using the gates above
- [ ] Deployment runbook written, with timings and owners
- [ ] Final data migration completed and reconciled
- [ ] Integrations switched to production endpoints
- [ ] Smoke test of the top 10 tasks in production
- [ ] Support channel live, with named people on call for the first week
- [ ] Rollback plan written and understood
Gate: smoke test passed and sponsor confirms go-live.
Phase 8: hypercare (weeks 13 to 16)
- [ ] Daily check-ins for week 1, then twice weekly
- [ ] Issue log triaged daily
- [ ] Adoption measured: logins, records created, reports used
- [ ] Quick fixes released weekly
- [ ] Handover documentation completed
- [ ] Next-phase backlog agreed
The 12-week plan template
| Week | Focus | Key deliverables | Owner |
|---|---|---|---|
| 1 | Discovery | Sponsor kickoff, process workshops | Project manager |
| 2 | Discovery and design | Signed scope, success measures, story backlog | Project owner |
| 3 | Design | Data model, security model, integration design | Solution architect |
| 4 | Design sign-off, sprint 1 starts | Design walkthrough signed, sandboxes ready | Architect, admin |
| 5 | Build sprint 1 | Core objects, layouts, first automation | Build team |
| 6 | Build sprint 1 demo, data trial 1 | Sprint demo, first trial migration | Build team, data lead |
| 7 | Build sprint 2 | Integrations, remaining automation, reports | Build team |
| 8 | Build sprint 2 demo, system test starts | Sprint demo, QA testing | QA lead |
| 9 | Testing, data trial 2 | Integration tests, second trial migration | QA, data lead |
| 10 | UAT | Business testing and defect fixes | Project owner |
| 11 | Training, cut-over prep | Role-based training, runbook, go/no-go | Trainer, project manager |
| 12 | Go-live | Final migration, deployment, smoke test | Whole team |
Copy it into a spreadsheet, adjust the weeks to your scope, and add a row for every integration.
Who you need on the team

A 12-week project at this size usually needs a project manager, a solution architect, 1 or 2 consultants or admins, a developer if there’s Apex or integration work, and a data lead. On the client side, a project owner and a subject-matter expert from each team in scope.
Our breakdown of implementation team hours by role shows how the effort typically splits.
When the checklist is too much
If you’re a small team starting fresh, a fixed-scope Salesforce Quickstart covers a slimmer version of this checklist in a few weeks. The phases stay the same. The number of stories, integrations and data sources shrinks.
A worked example from our own projects
Our prospecting tools case study followed 5 phases (discover, architect, build, enable, then a tuning phase after launch) that map closely to this checklist. The part that made the difference was phase 1: agreeing stage definitions and the SDR-to-AE handoff before anything was built.
Frequently asked questions
1. What should a Salesforce implementation checklist include?
At minimum: discovery (sponsor, scope, success measures), design (data model, security, automation, integrations), build in sandboxes, data cleansing and trial migrations, system and user acceptance testing, role-based training, a go-live runbook with rollback, and a hypercare period. Each phase needs an exit gate so problems are caught before the next phase starts.
2. How long does a Salesforce implementation take?
A mid-sized Sales Cloud or Service Cloud rollout with 50 to 200 users, 1 or 2 integrations and a data migration usually takes around 12 weeks, plus 4 weeks of hypercare. Small, fixed-scope projects can go live in a few weeks. Multi-cloud or enterprise projects often take 6 months or more.
3. What’s the most common reason Salesforce implementations slip?
In our experience, unclear scope at the start and late data work. Scope that isn’t signed off in discovery keeps growing through build, and data that isn’t profiled until the final weeks surprises everyone at migration. Running trial migrations from week 6 and enforcing a signed out-of-scope list prevent most delays.
4. Do we need a partner to use this checklist?
No. An experienced internal admin and project manager can run a smaller project with this checklist. A partner helps most with architecture, integrations, data migration and capacity, especially when the internal team is also running the business day to day.